New €595,600 roundabout for Protaras

Date:

A new traffic roundabout will be built at the busy intersection of Kavo Greko Avenue and Thali Street (near Lidl) in Protaras, Paralimni.

The Ministry of Transport announced that the contract was signed on Wednesday 26 November 2025 between the Department of Public Works and contractor Adelfoi Katsiou (Styliotes) Ltd.

Project details

  • Internal diameter: 15 metres
  • Two lanes, each 3.75 m wide
  • External pavement minimum 2.85 m wide
  • Inner island with 2 m wide paving blocks
  • Full street lighting by EAC
  • Irrigation system, road markings, telecom & water works

Timeline & cost

  • Works start: December 2025
  • Duration: 4 months
  • Cost: €595,600.79 + VAT

The new roundabout aims to improve traffic flow and safety on one of the area’s busiest roads.


Also read: Protaras parking free until end of March 2026

For more videos and updates, check out our YouTube channel https://www.youtube.com/@sigmaliveen.

Share post:

Popular

More like this
Related

Too Busy to Eat Well? Here’s How to Fix Your Diet Without Finding More Hours in the Day

Between early meetings, endless emails and late commutes, eating...

Foot and mouth disease probe focuses on feed from occupied areas

Authorities are examining the possibility that the transmission of...

On this day: First American Orbits the Earth

On February 20, 1962, the United States marked a...

George Georgallis book featured on London bus

Literary debut gains visibility in UK capital A book by...